INFORMATION FROM NATIONAL HIGHWAYS
We’ll be carrying out surveys to the drains to determine their current condition, along with low level maintenance work. This will ensure the drains are working as designed or help us to identify areas that are in need of repair.
We’ll work overnight, between 8pm and 6am, 25 March 2024 to 10 May 2024, Monday to Friday. Our work will be carried out as follows:
25 March to 27 March and 2 April to 5 April – Temporary traffic lights on the A483 between Mile End roundabout and the B5069.
8 April to 19 April – Full closures of the A483, in both directions, between Mile End roundabout and the A495/B4396/A483 junction.
22 April to 10 May – Temporary traffic lights on the A483 between Mile End roundabout and the B5069.
During closures we’ll install a fully signed diversion route via the A483, the A458 and the A5.
Access for emergency services will be maintained throughout.
We’ll make every effort to ensure the impact on the local community and travelling public is kept to a minimum. We always aim to work to the programme, however unforeseen circumstances or adverse weather conditions may mean changes.
I’d like to apologise in advance for any inconvenience or disruption to those living close to the work. We’ll make every effort to carefully manage noise levels and additional lighting to minimise the impact.
Further Information
If you’d like to be kept up to date with future work along the A483, please subscribe to our mailing list by emailing noreplyA483WMids@nationalhighways.co.uk.
If you have any questions, or if you would like to know more about our work, please call us on 0300 123 5000 or email info@nationalhighways.co.uk.
You can also visit our website at nationalhighways.co.uk/our-work/ or write to us at National Highways, National Traffic Operations Centre, 3 Ridgeway, Quinton Business Park, Birmingham, B32 1AF. Please leave your feedback by completing our online survey, just scan the QR code below.